Sending...
  • Vietnamese English

Lượt truy cập hôm nay: 407

Lượt truy cập hôm qua: 1034

Lượt truy cập tháng: 172285

Tổng truy cập: 3362752

  • Vietnamese English

Process of Project Management Consulting and Supervision consultancy Factory C-Kyocera Vietnam Office Machine Technology Co., Ltd.

On 11/6/2020, the project progress of Project Management Consulting and Supervision consultancy Factory C-Kyocera Vietnam Office Machine Technology Co., Ltd. Hai Phong reached the plan as required by the investor.
- 1st floor completed 97%, walling 5%
- 2nd floor completed 70% of the structure
- 3rd floor completed 45% of the structure
- Infrastructure completed 73%

Some pictures at the construction site

Project

Other news