Process of Project Management Consulting and Supervision consultancy Factory C-Kyocera Vietnam Office Machine Technology Co., Ltd.

On 11/6/2020, the project progress of Project Management Consulting and Supervision consultancy Factory C-Kyocera Vietnam Office Machine Technology Co., Ltd. Hai Phong reached the plan as required by the investor.
- 1st floor completed 97%, walling 5%
- 2nd floor completed 70% of the structure
- 3rd floor completed 45% of the structure
- Infrastructure completed 73%